MIRA - Bhaindar Road

Construction of Cement Concrete Road At

1) Mira Road East from Salasar Building to Rajmandir Complex.
(Length = 247.00 M, Width = 18.00 M)

2) Mira Road East Panel No. 13, from 15 No. S.T.P. to Reservation No. 287.
(Length = 296.00 M, Width = 18.00 M)

3) Manas OP Building to Kamlesh Nagar, Warkari Bhavan, at National Highway No. 08.
(Length = 296.00 M, Width = 15.00 M)

4) Kashimira Police Station to Hiraco Building, at National Highway No. 08.
(Length = 525.00 M, Width = 9.00 M)

5) National Highway No. 08. From Minakshi Nagar Tableta to Mashcha Pada
(Length = ___ M, Width = 18.00 M)

Client

Mira-Bhaindar Municipal Corporation

Location

Technical Drawings

Cement Concrete Roads, Mira-Bhayandar — Civikor page content

Civikor · Roads · page content

Cement Concrete Roads, Mira-Bhayandar

5 segments · 1,364 m confirmed · MBMC area

/mbmc-road-project-details/ Mira-Bhayandar Municipal Corporation ~989 words
Heads up: Wrong client on the /projects/ index card.

Five concrete roads across Mira-Bhayandar, including four on NH-08

Mira-Bhayandar Municipal Corporation appointed Civikor as project management consultant for a package of five cement concrete roads spread across the corporation's prabhag samitis — four of them fronting National Highway 08. One standard section, one drainage detail, five sites, delivered as a single coordinated programme.

At a glance

Project Construction of cement concrete roads at five locations in MBMC area
Client Mira-Bhayandar Municipal Corporation
Location Mira Road East, Kashimira and NH-08 frontage, Mira-Bhayandar, Dist. Thane, Maharashtra
Packages 5 road segments across multiple prabhag samitis
Confirmed length 1,364.00 m across four segments, plus segment 5 [CONFIRM]
Widths 18.00 m, 15.00 m and 9.00 m
Pavement 300 mm PQC in M40 grade over DLC and granular sub-base
Civikor's role Project management consultancy — DP marking, cross-section and drainage design, execution supervision
Status Ongoing

The five segments

# Location Length Width
1 Mira Road East — Salasar Building to Rajmandir Complex 247.00 m 18.00 m
2 Mira Road East, Panel No. 13 — 15 No. STP to Reservation No. 287 296.00 m 18.00 m
3 NH-08 — Man Opas Building to Kamlesh Nagar, Warkari Bhavan 296.00 m 15.00 m
4 NH-08 — Kashimira Police Station to Hiraco Building 525.00 m 9.00 m
5 NH-08 — Minakshi Nagar Tabela to Mashacha Pada [CONFIRM] 18.00 m
Confirmed total (segments 1–4) 1,364.00 m —

The brief

Mira-Bhayandar's growth has concentrated along National Highway 08 and the Mira Road East corridor — high-density residential blocks, commercial frontage and highway service traffic pressing on roads that were never built for that combination. Four of the five segments in this package front NH-08 directly, which means construction had to be sequenced around live highway movement rather than behind a closed corridor.

MBMC needed the segments rebuilt in cement concrete to a consistent corporation standard, with stormwater drainage designed as part of the road and pedestrian provision on both edges.

Scope of work

  • Development Plan marking across the corporation area — all five segments located on a single DP sheet against their prabhag samiti boundaries, so scope and jurisdiction were unambiguous from the outset.
  • Standard cross-section design — one 18.00 m typical section, applied consistently and adapted for the 15 m and 9 m segments.
  • Drainage design — encased RCC pipe drainage detail integrated with the pavement build-up.
  • Project management consultancy — quality assurance, measurement verification and progress reporting to MBMC across all five sites.

Pavement specification

Typical 18.00 m section — 1.00 m footpath + 1.50 m side strip + 6.00 m carriageway + 1.00 m central strip + 6.00 m carriageway + 1.50 m side strip + 1.00 m footpath, at 2% camber to both carriageways.

Element Layer Thickness / grade
Carriageway
top down
Pavement quality concrete (PQC) 0.30 m — M40
Dry lean concrete (DLC) 0.15 m
Granular sub-base I 0.25 m
Soling 0.23 m
Compacted existing subgrade —
Side strip / footpath Pavement quality concrete (PQC) 0.15 m — M40
Dry lean concrete (DLC) 0.15 m
Granular sub-base I 0.25 m
Granular sub-base II 0.15 m
Soling 0.23 m
Pedestrian finish Stamped concrete 75 mm
Kerb stone with water table M20
Edge drain RCC cover slab 150 mm — M25
RCC gutter pardi 150 mm — M25
RCC raft 150 mm — M25
PCC bedding 150 mm — M15
Soling 230 mm
Piped drainage RCC pipe 0.30 m dia
PCC encasing to pipe —
PCC bedding 0.15 m — M10
Soling 0.23 m

Drainage box section 2.00 m × 3.00 m with 0.45 m × 0.60 m pipe encasement, over murum sub-grade beneath the pavement layers.

How we approached it

One section, five sites

Five scattered segments could easily have become five separate designs with five separate quality standards. Instead a single typical cross-section and a single drainage detail govern the whole package, adapted only where the reserved width changes. For the corporation that means one specification to inspect against and one set of test criteria — the fastest route to consistent quality across dispersed sites.

Stamped concrete on the pedestrian edge

The side strips carry a 75 mm stamped concrete finish over a full PQC and DLC build-up. It is a pedestrian surface designed with the same structural seriousness as the carriageway, which matters on NH-08 frontage where footpaths are routinely driven over and parked on.

Drainage encased, not just laid

The 0.30 m dia RCC drainage pipe is fully encased in PCC beneath the pavement. Under a rigid slab carrying highway loading, an unencased pipe is a future settlement crack; encasement removes that failure mode at a marginal cost during construction.

Jurisdiction settled on one sheet

Marking all five segments on a single corporation-wide DP sheet, coded by prabhag samiti, gave MBMC a clear approval and monitoring instrument for a package that would otherwise have been tracked across five unrelated files.

Why it matters

  • Highway-grade construction on highway-adjacent roads. M40 PQC over DLC and a 0.25 m granular sub-base handles the service traffic that NH-08 frontage attracts.
  • Consistent quality across dispersed sites. A single governing section makes five separate construction fronts inspectable to one standard.
  • Monsoon resilience. Encased piped drainage plus continuous covered edge drains, in a corporation where waterlogging is the recurring annual failure.
  • Pedestrians designed for. Structural footpaths and kerb-with-water-table on both edges, not a strip of paving added at the end.
  • Whole-life value. Rigid pavement removes the recurring resurfacing cycle that consumes municipal road budgets.

Drawing set

  1. MBMC DP sheet marking, Mira-Bhayandar — all five segments located by prabhag samiti with legend.
  2. Typical cross-section of proposed roads (1:100) — 18.00 m section and plan.
  3. Cross section of drainage — encased RCC pipe and box drain detail.