Project Management Consultancy (PMC)

Strategic Infrastructure Optimization During Road Widening & Minor Bridge Development

How Civikor’s pre-execution review secured VJTI approval for a redesigned bridge and took the road corridor to its full 24 m sanctioned width.

  • Ambarnath Municipal Council, Maharashtra
  • Under Construction
Road widening project site in Ambarnath Road widening project site, Ambarnath

Project Management Consultancy

Project Brief

Civikor Consultant Private Limited was engaged as the Project Management Consultant for the execution supervision of a Road Widening and Minor Bridge Development Project.

Although the project’s DPR had been prepared by a third-party consultant, Civikor undertook a comprehensive technical and strategic review during the mobilisation phase to validate design assumptions, regulatory compliance, and long-term execution feasibility.

24 mRoad width now being delivered
12–18 mWidth proposed in the original DPR
VJTIProof-checking approval secured
Up to 12 mExtra width over the DPR proposal

Key Challenges Identified

During technical review and site assessment, Civikor identified critical discrepancies within the originally proposed project framework:

  • Bridge design needed statutory proof checking. The bridge design included in the DPR required proof checking and approval from VJTI prior to execution.

  • Major observations from VJTI. Technical scrutiny by VJTI resulted in major observations, necessitating a structural redesign of the bridge system.

  • Width short of the Development Plan. The DPR proposed a carriageway of 12 m to 18 m, while the sanctioned Development Plan (DP) defines the corridor as a 24 m wide road.

  • Conflict with long-term planning. The reduced width conflicted with long-term urban mobility planning and future infrastructure requirements.

Civikor's Value-Driven Intervention

Recognising the strategic importance of optimising the project before execution, Civikor delivered a multi-disciplinary intervention involving technical validation, stakeholder management and design enhancement:

Construction monitoring and supervision on the bridge site
1Statutory compliance

Bridge proof checking & redesign

  • Spearheaded the initiation and coordination process for bridge proof checking with VJTI.

  • Managed redesign and engineering modifications of the bridge structure in line with VJTI’s technical observations.

  • Secured proof-checking approval for the revised bridge design, ensuring statutory and structural compliance.

Site inspection and quality control along the road corridor
2Full-width corridor

24 m road development strategy

  • Conducted detailed corridor-level site verification to assess the feasibility of achieving the full 24 m DP road width.

  • Validated the absence of major physical encroachments within the proposed widening alignment.

  • Coordinated with industrial stakeholders for the voluntary adjustment of minor structures and landscaped areas within municipal boundaries.

  • Recommended and enabled execution planning for the revised 24 m road development strategy.

The Corridor at a Glance

What the DPR proposed, what the Development Plan sanctioned, and what is now being built.

Original DPR proposalWidth varied along the corridor
12–18 m
Sanctioned Development PlanCorridor defined in the DP
24 m
Civikor's revised strategyNow progressing on site
24 m · full DP width

Bars drawn to scale; the full bar equals the sanctioned 24 m corridor.

Project Impact

Civikor’s proactive intervention significantly enhanced the project’s technical viability and long-term strategic value by delivering:

Regulatory Compliance Assurance

Through VJTI-approved bridge proof checking and redesign.

Infrastructure Capacity Enhancement

By upgrading the road corridor to the full sanctioned 24 m width.

Future-Ready Urban Planning Alignment

Supporting long-term municipal traffic and development objectives.

Risk Mitigation

Through elimination of downstream redesign and execution conflicts.

Execution Readiness

With a technically validated, optimised construction scope now progressing on site.

Project Gallery

Visual documentation of project planning, execution, and supervision

Road widening project site
Construction monitoring and supervision
Site inspection and quality control
Project site documentation
Work in progress on site