Back to Case Studies
Project Management Consultancy (PMC)

Gravity-Led Drainage Network Planning & Execution Supervision at Kailash Nagar

How Civikor surveyed, planned and supervised a 1.1 km gravity drainage network through the narrow lanes of Kailash Nagar.

  • Ambarnath Municipal Council, Maharashtra
  • Kailash Nagar, Ambarnath West
  • Executed
Excavator trenching for the new drainage line in a Kailash Nagar lane Trenching along the main lane, Kailash Nagar

Project Management Consultancy

Project Brief

Civikor Consultant Private Limited was engaged as the Project Management Consultant for the Construction of Drainage Line at Kailash Nagar, in the Ambarnath Municipal Council area of Ambarnath West.

Kailash Nagar is a dense residential settlement of narrow lanes, with homes, shops and utilities built right up to the road edge. The project needed a network that could collect wastewater lane by lane and carry it to the nala on the settlement's edge — reliably, by gravity, and without long-term maintenance headaches.

Civikor led the work end to end: the ground survey, the strategic flow plan, and on-site supervision and quality control through execution.

1,125.89 mTotal drainage network
9Interconnected lines
648.80 mTrunk line to the nala
Every pipeLevel-checked during laying

Key Challenges Identified

During the site assessment, Civikor identified the conditions that would decide whether the network worked on day one — and for years after:

  • Very little natural fall. Ground levels drop only about 7 m across more than a kilometre of network, so every stretch needed a precisely set slope to keep wastewater moving by gravity.

  • Narrow, congested lanes. Excavation, pipe laying and machinery had to fit into gallis lined with homes and shops, while keeping residents' access open.

  • Existing services in the corridor. Electrical poles, city gas lines, existing drains, manholes and chambers sat along the proposed routes and had to be mapped before any digging.

  • Many branches, one outfall. Lines from nine different lanes had to join a single trunk line at the right levels and discharge into the nala without backflow.

Civikor's Value-Driven Intervention

Civikor treated the drainage line as an engineered system, not a trench-and-pipe job. The work moved through three connected stages:

Surveyor holding a levelling staff on a Kailash Nagar road Survey team recording an existing manhole level
1Ground truth first

Detailed topographic survey

  • Surveyed every lane in Kailash Nagar, from Toilet Galli and Morya Galli to Bathroom Galli and Khan Galli, recording ground levels along the full length of each proposed route.

  • Mapped compound walls, plinths, building and shed lines, trees and structures to fix a clear working corridor.

  • Located existing manholes, chambers, drains, electrical poles and city gas lines so the new alignment could avoid them.

Detail of the flow plan showing manhole levels and slopes along Toilet Galli, Morya Galli and Bathroom Galli
2Design the flow

Strategic flow plan

  • Planned the network as nine interconnected lines totalling 1,125.89 m, led by a 648.80 m trunk line to the nala.

  • Fixed the top and invert levels at every manhole, and the slope of every stretch, so the whole system drains by gravity.

  • Set branch junctions at levels that feed the trunk line smoothly, preventing backflow and stagnant sections.

Spirit level placed on a laid drainage pipe to verify its slope Drainage pipes being aligned in the trench during execution
3Build it as designed

Execution supervision & quality control

  • Supervised excavation and trenching lane by lane, keeping work within the surveyed corridor.

  • Checked the alignment of each pipe in the trench before joints were made.

  • Verified the level of every pipe during laying and matched it against the design slopes, correcting any deviation on the spot.

The Network at a Glance

Nine lines, one outfall. Each colour on the flow plan is a separate line, planned and measured on its own.

Project Impact

Civikor's survey-led planning and close supervision gave Kailash Nagar a drainage network that works as designed:

Gravity-Driven Flow

Precisely set slopes carry wastewater from every lane to the nala by gravity alone.

Level-Verified Construction

Every pipe was checked against design levels, so the built network matches the plan.

Risk Mitigation

Mapping utilities before digging reduced damage to existing services and rework on site.

Transparent Quantities

A line-by-line record of all 1,125.89 m gives the council clear, verifiable measurements.

Easier Long-Term Maintenance

Recorded manhole and invert levels give the council a reliable reference for future servicing.

Project Gallery

Visual documentation of survey, planning, execution and supervision

Pipe laying in the trench
Level check on a laid pipe
Trenching along the main lane
Pipe placed on the prepared bed
Level survey along a residential lane
Excavation in a narrow lane
Laid pipe before backfilling
Recording existing manhole levels
Joint and alignment inspection
Survey team in the field
Mapping the existing drain
Levelling on the approach road

Planning a Drainage or Sewer Project?

Let's discuss how Civikor can plan it right from the first survey to the last pipe.

Start a Conversation