MIDC Roads at ITI College

Construction of Cement Concrete Road from KB – Road, RL Chemicals Pvt. Ltd. to Occupational Health Center Towards Nalla Side, Ambarnath West, in AMC Area.

(Length = 330.00 M, Width = 18.00 M)

Client

Ambarnath Municipal Council

Location

Technical Drawings

MIDC Roads at ITI College — Civikor page content

Civikor · Roads · page content

MIDC Roads at ITI College

1,015 m · 3 packages · MIDC Ambarnath

/midc-roads-at-iti-college/ Ambarnath Municipal Council ~987 words
Heads up: Live page shows 1 of 3 packages.

Concrete roads for the ITI College sector, MIDC Ambarnath

Three separate links, five width classes and just over a kilometre of pavement — designed to give the chemical and pharmaceutical plants around ITI College a road surface that survives their traffic, and a corridor that keeps the sector's bus stop, fire hydrants and drains where they belong.

At a glance

Project Construction of cement concrete roads, MIDC Ambarnath — ITI College sector (MIDC II)
Client Ambarnath Municipal Council
Location MIDC Additional Ambarnath, near ITI College, Ambarnath West, Dist. Thane, Maharashtra
Packages 3 road links
Total length 1,015.00 m across all links
Widths 18.00 m, 15.00 m and 9.00 m classes
Pavement 300 mm PQC in M40 grade over DLC and granular sub-base
Civikor's role Survey, road estimate (RE) drawings, cross-section and duct design, project management consultancy
Status Ongoing

The three packages

# Link Length Width
1 KB Road, RL Chemicals Pvt Ltd to Occupational Health Centre, towards nalla side 330.00 m 18.00 m
2 Kanad Chemicals Pvt Ltd stretch — two legs 120.00 m 15.00 m
215.00 m 9.00 m
3 Bluejet Healthcare Pvt Ltd stretch 350.00 m 18.00 m
Total 1,015.00 m

The brief

The ITI College sector of MIDC Ambarnath serves speciality chemical and pharmaceutical manufacturers — RL Chemicals, Kanad Chemicals and Bluejet Healthcare among them — alongside the estate's Occupational Health Centre. It is a corridor where tanker movement, employee bus traffic and emergency access all share the same narrow set of internal roads, and where a road failure has consequences beyond inconvenience.

Ambarnath Municipal Council commissioned a rebuild in cement concrete, with the sector's existing drains, fire hydrants and bus stop surveyed and retained in the new layout rather than displaced by it.

Scope of work

  • Sector survey — all three links recorded, with existing drains, fire hydrants, structures and the bus stop fixed by chainage.
  • Road estimate (RE) sheets 1–3 — plan, longitudinal section and quantities for each link, referenced CH 0 onward.
  • Typical cross-sections for the 18.00 m, 15.00 m and 9.00 m width classes.
  • Cross duct and trial pit details — strata logged and service crossings positioned before the slab is cast.
  • Unit-wise location and Google location plans — issued separately for the RL Chemicals, Kanad Chemicals and Bluejet Healthcare frontages, plus a Google Earth key plan for the whole sector.
  • Project management consultancy through execution.

Pavement specification

Typical 18.00 m section — 1.50 m footpath + 2.00 m side strip + 5.50 m carriageway + 5.50 m carriageway + 2.00 m side strip + 1.50 m footpath, at 2% camber.

Element Layer Thickness / grade
Carriageway
top down
Pavement quality concrete (PQC) 0.30 m — M40
Dry lean concrete (DLC) 0.15 m
Granular sub-base I 0.15 m
Granular sub-base II 0.15 m
Soling 0.23 m
Footpath Paver block 0.10 m
PCC 0.15 m
Granular sub-base I 0.15 m
Filling 0.10 m
Side drain RCC cover slab 0.20 m — M25
RCC gutter pardi 0.25 m — M25
RCC raft 0.30 m — M25
PCC bedding 0.20 m — M15
Soling 0.23 m
Cross duct RCC pipe, NP2 class 0.30 m dia
Soil filling over pipe 0.60 m
PCC surround 0.15 m — M15

Kerb stone with water table to both edges. Trial pit strata logged as silt, clay and pebbles over soft murum.

How we approached it

Existing sector assets mapped, then designed around

A fire hydrant at chainage 155 m, a bus stop at chainage 175 m, an existing structure and multiple drain crossings — all fixed on the RE sheets before the alignment was finalised. On an operating industrial estate these are not obstructions to be removed; they are assets the sector depends on, and the road is set out to keep them accessible.

Two legs at Kanad Chemicals, sized separately

The Kanad Chemicals frontage splits into a short 15 m leg and a longer 9 m leg. Rather than averaging the two into one width, each is designed for the movement it actually carries — the wider leg where vehicles turn into the plant, the narrower one as a through connection.

Nalla-side drainage taken seriously

The RL Chemicals link runs toward the nalla. That gives the corridor a natural outfall, but only if the drain invert levels are set to reach it. Longitudinal sections were drawn chainage by chainage so the fall is continuous to the discharge point instead of ponding at the low chainages.

Ducts before concrete

0.30 m dia NP2 RCC cross ducts are cast in at every anticipated service crossing. A chemical plant adding a new utility connection should not require a saw cut through a two-year-old rigid pavement.

Why it matters

  • Emergency access protected. The link to the Occupational Health Centre is built to 18 m and its fire hydrant kept in service — on a chemical estate, that is the specification that matters most.
  • Built for tanker loading. M40 PQC over DLC and twin granular sub-base, on a subgrade verified by trial pits.
  • Sector treated as a system. Three links designed together, so drainage falls, junction levels and duct positions are continuous across the whole sector.
  • Public transport retained. The sector's bus stop is designed into the corridor at chainage 175 m rather than lost to the rebuild.
  • A surface that stays uncut — and therefore keeps its design life.

Drawing set

  1. ITI College MIDC II Google Earth location plan — sector key plan.
  2. RE sheets 1, 2 and 3 — chainage-wise plan, longitudinal section and quantities.
  3. Location and Google location plans — RL Chemicals, Kanad Chemicals and Bluejet Healthcare frontages.
  4. Typical road cross-sections — 18.00 m, 15.00 m and 9.00 m width classes.
  5. Section of cross duct and trial pit — service crossing detail with logged strata.